You are here: HOBAS Pipe
Miles of HOBAS Installed in Odessa

go back

HOBAS pipes were utilized on two major phases of a wastewater piping project in Odessa, TX. One phase included expansion of the East Water Reclamation Plant (EWRP) to prepare for increased flows. The other phase was the construction of a transfer line which diverts flow to the EWRP from the South Dixie Water Reclamation Plant (SDWRP), which was to be abandoned.

Limited Specification
The specifying engineers for the EWRP modifications were Landgraf, Crutcher and Associates, Inc. (LCA) of Odessa, TX and Alan Plummer and Associates, Inc. (APA) of Fort Worth, TX. The engineers' specifications allowed both HOBAS pipes and ductile iron pipes although, due to the corrosive environment, D.I. pipes were required to have an epoxy-lining as well as a complete polyethylene encasement bag for direct burial. HOBAS pipes did not require additional linings or coatings due to their inherent corrosion resistance which results in superior performance in acidic conditions (such as those found in many sanitary sewers). Either low pressure air or hydrostatic field testing was required to ensure integrity of line after installation.

Special Aerial Design
The installation contractor for the Bob Derrington Water Reclamation Plant (new name for the modified EWRP) was The Hardaway Company of Tampa, FL. Approximately 7,000 ft. of 46 psi stiffness pipe ranging from 18" to 54" was supplied with HOBAS gasket-sealed FWC couplings for installation by direct bury. Many fittings were fabricated for the treatment plant including lateral wyes, tees, elbows, reducers and flanges. A specially designed 48 inch diameter, 72 psi stiffness pipe was manufactured for the sanitary sewage aerial installation. The two parallel above ground lines totaled 1,740 ft. and were placed on concrete cradles spaced at approximately 20 ft. centers. The aerial included a 90 degree turn which required fabrication of two special elbows (one long and one short radius) to maintain the parallel alignment.

Engineered Product
The Odessa Transfer Sewer Interceptor, which diverts the sewage from the South Dixie plant to the new Bob Derrington plant, includes over 7 miles of 54" and 48" pipe which is being installed by Oscar Renda Contracting, Inc., of Roanoke, TX. The majority of the pipe was installed by direct bury at cover depths of up to 28 ft. Other installations included 3,200 ft. of 54" 500 ton flush joint pipe installed by jacking and approximately 300 ft. in a casing. The open cut pipe stiffness classes ranged from 18 psi to 72 psi, changing as appropriate with increased depth, resulting in the safest, least costly installation. Since HOBAS is an engineered product, different stiffness classes or jacking tonnages are easily manufactured to meet job specific design criteria economically.

Meets ASTM Specs
LCA and APA were also the engineers for the Odessa Transfer Sewer and again specified corrosion resistant piping products, due to the anticipated acidic environment including; fiberglass reinforced pipes (FRP), ductile iron pipes with a 40 mil polyethylene liner (DI-PE), and reinforced concrete pipes with 360 degree T-lock lining (RCP-PVC). The specifications required that all materials conform to various ASTM and AWWA standards.

All Fiberglass MH's
Over 30 HOBAS T-base manholes, both straight and P.I., were supplied with 30 in. riser stubs to receive 48" diameter fiberglass manholes manufactured by L.F. Manufacturing of Giddings, TX. Due to our unique fabrication process the T-base sections were fabricated to exactly the angle required whether it be 88 degrees left or 4 degrees right. Since the manholes are manufactured from either straight or mitered sections of our centrifugally cast pipe, they were easily joined into the line with the FWC coupling to create a completely gasket-sealed HOBAS system.

High Performance
The HOBAS fiberglass sleeve couplings (FWC), which utilize elastomeric sealing gaskets made of EPDM rubber, contributed to the rapid laying rates and resulted in the absolutely leakfree joints achieved on the transfer line. Almost 1,000 joints (19,000 ft.) of 48 in. diameter pipe were laid in 30 days. Even with the accelerated laying rate, HOBAS pipe joints were air tested at 3.5 psi with a 100% pass rate on the first test. In fact, the pressure tests showed no leaks at all, exhibiting zero pressure drop during the test period. Deflection tests revealed that most of the pipe has less than 1% deflection with the maximum being 1.5%. (Considerably less than the recommended maximum of 5%.) Oscar Renda Contracting is very happy with the performance of the HOBAS pipes and the user friendly installation, even under accelerated laying conditions
.

go back

2008 Upcoming Tradeshows
SHOW DATE

BOOTH

ACE 08
Atlanta, GA
Jun 8 - 12 116
ASCE
Atlanta, GA
July 22-24 TBD
APWA
New Orleans, LA
Aug, 17-19 1510
WEFTEC 08
Chicago, IL
Oct. 18-22 23003

Home    Product Info    News    Tech Profiles    Case Histories    Video Clips    Product Brochure    Contact