HOBAS pipes carry
the flow for the Trinity River Authority in their new 72"
diameter Jefferson Ave. Relief Tunnel. The two-mile long sanitary
sewer line extends south from I-30 in Grand Prairie, Texas and
provides badly needed additional capacity.
Challenging
Design
Design and construction of the line presented many challenges.
Because of the depth (mostly in excess of 70 ft.) and the
alignment (beneath a military facility and an established
residential neighborhood), tunneling was the only feasible
installation method. The difficulty of this procedure was further
increased because access shafts were limited to both ends and
fully half of the distance is in radius curves. In addition to
these items, project designers, Black & Veatch of Dallas, also
faced durability, leakage control and structural design issues.
Limited
Specification
In order to assure the structural performance, the allowed
waterway carriers, HOBAS pipes, RCP or cast-in-place concrete were
required to carry all long-term loads without aid from the initial
tunnel supports. Durability, inherent for HOBAS pipe, was achieved
for the concrete products by requiring a corrosion liner of PVC or
HDPE. Specifications also limited leakage with a 125 inch-gallon
infiltration test; easy for the no-leak HOBAS gasket-sealed,
bell-spigot joints.
Big
Savings
HOBAS pipes were selected by Oscar Renda Contracting of Roanoke,
Texas, for several cost saving reasons. The high strength, much
thinner pipe walls permitted the tunnel to be about one foot
smaller. This resulted in fewer initial tunnel supports, over 20%
less excavation and a smaller, less expensive bore head.
Additionally, the lightweight (15% of RCP) HOBAS pipe could be
inserted the required long distance (5,000 ft.) much easier,
faster and cheaper. Finally, all of the planned radius curves
could be constructed using 20 ft. pipe sections because of the
1.25 degree joint angular deflection capability.
Successful
Installation
Due to the many curves, the pipes were inserted individually,
carried-in on a specially designed cart. This allowed rapid
placement utilizing the same train engine that had been earlier
used to power the muck cars. The pipes were belled in place with
an electric jack and then were strategically blocked across each
joint to the ceiling and sidewalls of the tunnel. The installation
was completed by annular space grouting accomplished in two lifts
due to the pipe's high strength and stiffness. The finished
pipeline is solid, leak-free and has little deflection; much to
the pleasure and satisfaction of all involved.