New higher levels
of accomplishment saving money, time, and disruption were achieved
during the sliplining rehabilitation of J.O. "B" Unit 1C
(Phase 4) in County Sanitation District No. 2 of Los Angeles
County (LACSD). On this project, nearly 10,000 ft of existing
deteriorated 57" and 63" RCP interceptor was relined
with 51" and 57" HOBAS fiberglass pipes using innovative
installation methods suggested by the contractor, Cook
Construction of Downey, CA. Cook's creativity and skilled
execution, LACSD's cooperation and willingness to allow worthy new
procedures, and the superior performance of HOBAS pipes all
contributed to the high achievements. These included sliplining of
several tight radius curves, reducing the number of pits from
seven to four by pushing long distances and through PI's, and
eliminating two structures and a jacking section.
Specific Needs
Like past LACSD rehab projects, this liner also had to be
installed without by-pass pumping of sewage flow. Additionally, a
pipe stiffness of 46 psi minimum was required for safe annular
space grouting collapse resistance. This pipe class had to be
achieved with an OD that would enable a low-risk insertion fit and
with an ID not more than 6" smaller than the host pipe to
assure adequate flow recovery. As typical, the liner had to be
resistant to future sulfide attack and have flush, gasket-sealed
joints for fast assembly, leak-free performance and a smooth
exterior surface. These critical needs again resulted in an
exclusive specification for centrifugally cast fiberglass
reinforced polyester mortar pipe (HOBAS or equal).
Curves Sliplined
Three curves, each with a 45 ft. radius, were sliplined using
about 175 ft. (total) of 2.5 ft. long sections of HOBAS pipes. The
push shafts were purposely located so the curved areas were at the
ends of the drives. The short pieces were inserted first, followed
by 20 ft. pipes for the straight portion of the line. This was
successful even on a 3,500 ft. distance with seventeen 2.5 ft.
sections at the front. Because the curves actually consist of
mitered pipes, a few of the liner's gasketed joints have angular
deflections greater than their design capability. However, the
joint gaps were sealed in place by fabricating reinforced overlays
across the affected joints on the interior. This work was made
possible by LACSD temporarily diverting the flow for a few hours
overnight. The curve sliplining achievement eliminated the need to
open-cut those areas to accomplish the relining.
Huge Savings
One of the curves is located under I-5. Plans called for a
parallel jacked installation with two new diversion structures to
reconnect the ends to the original line. Because of earlier
successes, LACSD allowed Cook (home office in Albuquerque) to
slipline the curve under I-5 too. This change saved over $300,000
which was split between the agency and the contractor according to
the value engineering procedure.
High Performance
On the fourth push, approximately 1,800 ft. long, a four degree PI
1,000 ft. from the drive pit was sliplined. Mandrel proofing
confirmed that 10 ft. sections would pass through this angle
point, so the lead 800 ft. inserted consisted of that length
section followed by 20 ft. pipes. Despite pushing through curves
and PI's, the approximate average friction factor for the entire
job was 0.3 with a range of 0.25 to 0.50, which is typical. In
fact, the maximum pushing force was only about 100 tons, even for
the longest drives. So easy are the pipe assembly and insertion
that sustained installation rates of 260 ft./hr. were achieved,
even with the live sewage flows present.
Versatility and Success
HOBAS also supplied a 57" to 51" eccentric reducer and
33" pipes to line the 36" manhole risers. A field
lamination was made to connect the new risers to the main pipes.
Because of HOBAS pipes' versatility and the continued high success
of rehabilitation jobs, four additional LACSD sewer projects using
HOBAS pipes are currently in various stages of progress. If you
too have sewer renovation needs, contact us today.